Quaker Road to Remain Closed for Week of March 21

Pavement repairs on Quaker Road are scheduled to take place starting on March 21. The project is expected to take about four days to complete.

The work will be done in two sections. The first section is from Port Mercer to Mercer Road, and the second section is from Mercer Road to Route 206. The intersection of Mercer Road and Quaker Road will remain open while the repairs are being made.

Work will start at Port Mercer and proceed north towards Mercer Road, and then from Mercer Road towards Route 206.

No work will take place on the weekends or holidays and the road will be open on those days. In the event of inclement weather, the work will proceed the following business day.

Provisions will be made for continued services such as brush collection, mail delivery, garbage, recycling pick-up and school buses. The road will be reopened to through traffic at the end of
each work day and will remain open until the start of next work day.